Photos of holes and filled in holes are not very interesting, so the blog has been quiet for a few days. The drive and garage base are now finished with electric/gas ducting going between the garage and the house.

The re-enforced concrete from the barn has been broken up and transported off site, and the hardcore underneath recycled as part of the drive.

Now we move to the next stage which is dealing with sewerage – no mains drainage here. So a large 3m deep hole was dug for this concrete tank.
Sceptic Tank
Not that much shows once it is filled in – looks rather like a submarine. Apparently they went through 4 layers: Topsoil, yellow stony “head”, red mudstone and finally reaching a clay.