Oh dear – windows

We thought we were doing so well with the windows – they arrived in time for the build and they seem to be the correct number and size, but in true “Grand Designs” fashion we have encountered a little problem. All bar two of the opening windows and the patio door have their hinges on the wrong side.
As far as I can work out, it is a bit like the Mars Orbiter which missed Mars because one team worked in pound-seconds(Lb/s) and the other team worked in newton-seconds. This is what a window looks like at the plan stage – it is viewed from the outside and the point of the dotted V shows where the hinge is. Window PlanUnfortunately the window manufacturer does it different. The windows are viewed from the inside and the V point is where the handle is. Some-where along the supply line the drawings were incorrectly converted, though not consistently as not all the windows are wrong.

Fortunately we can work round it – two opening windows are fortunately the same size and can be switched. Other ones it did not really matter which way they opened. The biggest change has been to the patio door where the drawings shown the door on the left (as viewed from the inside). And as you can see from the photo it is now on the right.
Patio DoorWe had a session making sure it would not impact on where furniture could be put and on the whole it seems it might be the better place for it any-way.

First Windows and Walls

The biggest visual changes this week have been to Mike’s study, which now has a first layer of wall, a ceiling and three sets of windows.StaircaseThe dark space behind the temporary staircase is the study and you can just see one of the corner windows and the front window. The next photo shows the house from the front drive with the study window on the right. The front door will be where the big gap is on the left of the photo.

Pod Front
Front of house
Having the staircase means that both us and the cat now have easy access on to the first floor, where you can get a feel of the two interlocking cubes that make up the house.
Pod roof
Pod roof on right, staircase on left
Other jobs have continued around the rest of the house with flooring now covering all the first floor joists and the start of fixing the slates around the base of the house. The wood cladding will not reach the ground in order to prevent rotting, but will overlap these slates.
Slate Edging
Slate Edging

Taking Shape

This week the frame has been working its way round the rest of the ground floor. If you look at the house plans you can see that the house is the intersection of two cubes, which makes for a tricky wall where the two cubes intersect. This is particularly true where the west wall of the first floor does not have a ground floor wall below. The first photo shows the beam running from north to south which will support the west first floor wall.

West First Floor Beam
West First Floor Beam
The next photo shows the frame for Mike’s pod with the west wall beam jutting out on the left to form one side of the triangular overhang of the porch.
Pod Frame
Pod Frame
Not only has the outside ground floor frame be finished, but two-thirds of the first floor has been laid. This photo show the ventilation ducting threaded through the joists under the floor.
MVHR Ducting
MVHR Ducting

House Build has started

After weeks of ground preparation, the frame of the house has started going up. The photo shows the I-beams forming the frame of the ground floor. One side of the I-beam rests on the concrete foundation and then cantilevers over the insulating polystyrene which surrounds the concrete. Stacked up on the concrete floor is the rest of the house in kit-form.

I-Beams Ground Floor Frame
I-Beams Ground Floor Frame
The I_beams have also been used horizontally to produce the base for Mike’s study which is cantilevered off some concrete piles. It is covered in plastic in the previous photo.
Pod Floor
Pod Floor
And so what is an I-beam. It is a mixture of OSB board and wood in an I-shape. Here is a close-up of one.
I-Beam Cross Section
I-Beam Cross Section

Scaffolding

The last few days have seen the scaffolding go up, which has given us our first indication of the height of the new house. The top boards are just below the roof at its low end on the left and a metre below at the high end.

Scaffolding
View of scaffolding from the orchard
Despite “Grand Designs” habitually having problems of windows arriving late, ours have arrived before the start of the build. However, as it was discovered that they were being transported on a large artic with no crane, they have been offloaded in Pershore and will stay there over Christmas awaiting a smaller lorry with a suitable crane.

Concreting

Wednesday was the day for concreting the foundations, so it was all hands on site as it had to be smoothed out before it started to set.

Concreting
Concreting

From start to finish it took a couple of hours, but speeded up it only takes 16 seconds.

And Mike has been try out his helicopter flying for an aerial view of the site.

Polystyrene foundations

The photo shows the pale pink slot-together polystyrene system which provides the insulation around and below the concrete foundations for the main part of the house.
Lego So we are now ready for pouring the concrete next week.

Here is a video of the polystyrene going down:

Ground Works Week 8

For a change this week, there has been movement out of the ground instead of holes being dug and filled in. These are the pillars which will hold up the cantilevered floor of Mike’s study.

Pod Pillars
Pod Pillars

Ground Works Week 7

More trenches being dug this week – water to one corner of the field and electricity to the other.

Water_Trench
Water Trench
Only one small surprise when the existing electricity turned out to be not where the plans from the electricity company said it was.
Water and Electricty
Water and Electricity

Ground Works week 6

Another two weeks of digging holes and filling them in. Septic SpreaderThis is a photo of part of the one of the two 25m long septic tank spreaders which wander into the wood. All now covered up and hopefully will silently work over the next few decades.

And now we start to see the shape of the new house for the first time.House RaftThe photo is taken from the corner of Mike’s “pod” looking through the shower room to the kitchen and living room.